6. Hand Over to Customer
6.1 Operational Steps
Important Points
a) The measurements taken during the test run should be recorded and kept on a test run inspection
sheet.
b) Do not forget to record the
length of the refrigerant piping
and the
refrigerant additional charging
volume
on the plate on the back of the outdoor unit external notice board, as this information will be
required for servicing the system.
c) Explain to the customer how to operate the equipment and let him try it.
d) Assemble all the relevant diagrams and other printed matter which is required to operate the system
and hand it all over to the customer (on the spot) and tell him to keep it.
e) Make the service contact address clear.
Complete test run
Make final report
(test run
inspection sheet)
Explain how to
operate
equipment
Hand over relevant
printed materials
(V1050)
List of equipment which has been
delivered
Contract drawings
Names of those responsible for the
work (emergency contact address)
Equipment guarantees
1 set of operation manuals
It is essential to prepare a control wiring diagram
which clarifies the refrigerant system and the
control system.
System design documents
Customer
Содержание RXYQ5PY1
Страница 2: ......
Страница 287: ...SiEN34 705 Heat Pump 60Hz RXYQ5 54P Installation Manual 281...
Страница 292: ...Heat Pump 60Hz RXYQ5 54P SiEN34 705 286 Installation Manual...
Страница 339: ...Operation Manual SiEN34 705 332 Operation Manual...