Upgrading a Multicarrier G2 Universal Module to Avaya
DEFINITY Server R EPN running Avaya Communication
Manager
555-233-115
5-104
Issue 7 November 2003
For Two Collocated Expansion Port Networks
1. Behind control carrier A of PPN cabinet 1:
■
Install a lightwave transceiver on the cable connector at slot 1A02.
NOTE:
Attenuators may be required for single mode fiber using a
300A Lightwave Transceiver
■
Connect a fiber optic cable to the transceiver just installed.
■
Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
2. Behind control carrier A of EPN cabinet 3:
■
Install a lightwave transceiver on the cable connector at slot 3A01.
NOTE:
Attenuators may be required for single mode fiber using a
300A Lightwave Transceiver
■
Connect the other end of the fiber optic cable to the lightwave
transceiver just installed.
■
Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
■
At the top of the cabinet, coil up the surplus fiber optic cable and
attach it to the wall of the cable tray.
3. Behind control carrier A of EPN cabinet 2:
■
Install a lightwave transceiver on the cable connector at slot 2A02.
■
Connect a fiber optic cable to the transceiver just installed.
■
Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
4. Behind control carrier A of EPN cabinet 3:
■
Install a lightwave transceiver on the cable connector at slot 3A02.
NOTE:
Attenuators may be required for single mode fiber using a
300A Lightwave Transceiver
■
Connect the other end of the fiber optic cable to the transceiver just
installed.
■
Carefully attach the fiber optic cable (with cable ties) to the wall of
the cable tray at the built-in cable tie positions.
■
At the top of the cabinet, coil up the surplus fiber optic cable and
attach it to the wall of the cable tray.