Installing a Profiling Thermocouple in Vacuum Systems
1. Slide the profiling thermocouple into the tube case so that the centerlines of
heating cassette and internal element align. Use the two stud screws to fix the
position within the aluminum stop.
2. Clean the tube case and the O-rings in the feedthrough.
3. Slide the profiling thermocouple through the vacuum feedthrough into the process
tube.
4. Manually tighten the milled nut of the vacuum feedthrough.
5. Connect the thermocouple connector to the measuring amplifier and close the
cover.
9.5.4
Installing the Spike Thermocouple
1. Slide the spike thermocouples in the tube cases into the heating cassette until they
touch the process tube. Three to five pairs of thermocouples are installed in the
equipment depending on the number of heating zones.
2. Use spring clips to secure the spike thermocouples against sliding out.
3. Connect the first spike thermocouple to the temperature measuring module
(TMM6).
4. Connect the second spike thermocouple used for temperature monitoring to the
overtemperature sensor.
9.6
Connecting Gas System and Process Tube
CAUTION!
Adjust the soft landing system (SLS) first and then the heating cassette, before
connecting the gas system. Changing the sequence can damage or even destroy the
connections.
9.6.1
Installing the Synthesis Steam Generator (Option)
The assembly of the synthesis steam generator is described in the operating
instructions of the synthesis steam generator, see chapter 12.5 Information on the Gas
System, page 12-2.
Summary of Contents for E1200 HT 260-3
Page 1: ...Operating Instructions for Horizontal Furnace Equipment E1200 HT 260 3 Version 1 0 1_41087 11 ...
Page 2: ...E1200 HT 260 3 23 04 07 00401010_41087 ...
Page 4: ...E1200 HT 260 3 Document Information 23 04 07 00401010_41087 ...
Page 16: ...E1200 HT 260 3 Index 23 04 07 00401010_41087 ...
Page 18: ...E1200 HT 260 3 List of Figures 23 04 07 00401010_41087 ...
Page 20: ...E1200 HT 260 3 List of Tables 23 04 07 00401010_41087 ...
Page 26: ...E1200 HT 260 3 0BOperating Instruction Remarks 23 04 07 1 6 00401010_41087 ...
Page 34: ...E1200 HT 260 3 1BIntroduction 23 04 07 2 8 00401010_41087 ...
Page 50: ...E1200 HT 260 3 2BSafety 23 04 07 3 16 00401010_41087 ...
Page 78: ...E1200 HT 260 3 4BTransport 23 04 07 5 4 00401010_41087 ...
Page 180: ...E1200 HT 260 3 8BMaintenance 23 04 07 9 76 00401010_41087 ...
Page 228: ...E1200 HT 260 3 10BSpare and Wearing Parts 23 04 07 11 2 00401010_41087 ...