Chapter 8 Replacement procedures
8 - 191
8-7-4-4
Calibration and adjustments
No calibrations or adjustments are needed after this part replacement.
8-7-4-5
Verification
Perform the following steps to verify that the product is functioning as intended after this replacement:
1.) Verify that all screws removed earlier have been installed.
2.) If finished, connect cables and Probes removed earlier.
3.) Power up the system to verify that it operates as intended.
4.) Verify that there is no unusual noise from the Fan Assembly.
8-7-4-6
Functional Checks
Perform the following functional checks to confirm the system is operational before returning the system
to the customer.
If all are successful, include the following debrief script: LOGIQ E9 Service Manual, Direction
5535208-100, Rev. 2. Equipment passed all required checks and is ready for use.
Table 8-117 Fan Assembly replacement Functional Checks
See:
Section
Functional Check
Debrief Script
4-2-2
Power ON/Boot Up
LOGIQ E9 Service Manual, Direction
5535208-100, Rev. 2. Equipment passed all
required checks and is ready for use.
4-2-3
Power shut down
4-3-14
Probe/Connectors Checks
4-3-5
B-Mode Checks
4-3-7
System CFM and PWD Checks
4-3-18
Mechanical Function Checks
Содержание 5205000
Страница 1: ...10 20 14 GEHC_FRNT_CVR FM LOGIQ E9 SERVICE MANUAL Part Number 5535208 100 Revision Rev 2 ...
Страница 2: ......
Страница 21: ...GE DIRECTION 5535208 100 REV 2 LOGIQ E9 SERVICE MANUAL 19 ZH CN KO ...
Страница 198: ...GE DIRECTION 5535208 100 REV 2 LOGIQ E9 SERVICE MANUAL 4 54 Section 4 8 Site Log This page was intentionally left blank ...
Страница 807: ......
Страница 808: ......