3.1 Introduction
This chapter describes the installation of ChemGuard® CG050 GEN III cabinet.
Because each customer application may vary, these instructions are provided as a
guideline and should not be considered as comprehensive.
Please do not begin installing the ChemGuard® unless trained individuals are
present.
The ChemGuard® CG050 comes pre-calibrated and cabinet-tested. The
ChemGuard® Bulk Scale, dual float spill detector, combustible vapor detector
(option) and UVIR (option) are setup prior to leaving the factory. These items
should not require calibration during installation. Please contact Versum Materials,
Inc. if any of these components do not function properly.
NOTE:
When highly flammable chemicals are used and present within
the equipment you must:
•
Ensure the all connections made to the cabinet are leak tight.
•
Use an inert gas purge to dilute the concentration of highly
flammable vapors in the exhaust header to which the vent
piping is connected.
•
Use an inert gas purge to the vacuum pump gas ballast
connection.
3.2 Reference Documents
For Installation and P&ID system drawings, facilities inspection, pre -startup and
commissioning procedure and check-off/sign-off lists refer to;
•
SW017054_Installation Drawing
•
DOC000191 for the ChemGuard® CG050 GEN III P&ID Drawings
•
V-TSA060_ChemGuard® Chemical Fill Matrix