Addendum A
– LPE 14 Liter Bubbler Change
MNL000629.doc
Revision 0
06/25/2019
Chemical Equipment
© Versum Materials, Inc. as of the revision and date shown. All rights reserved.
Confidential and Proprietary Data
AD A-
4
b)
Wrenches (5/8 in., 11/16 in. and 3/4 in. open end)
c)
6.35mm ( ¼ in.) stainless steel, VCR gaskets
d)
Proper personal protective equipment
2. Put on personal protective equipment.
1.3 Change BULK Bubbler Operation (not available for 38L
Bubbler option)
Changing the Bubbler
This option guides the operator through steps to remove and replace 14 Liter LPE
Bubbler. Change BLK operation must be performed any time to remove or install
the Bubbler.
To start Change BLK operations:
•
At Main Menu scroll to CHEM ON
•
Select START CHANGE BLK button
•
Confirm Sequence Start confirmation
button will be displayed
•
Select the Confirmation button to start
Change Blk Operation
Change Bubbler operation will not proceed if any of the following conditions exists:
•
CHEM ON or External Fill is enabled
•
The Vacuum Venturi is not turned on
•
A Shutdown alarm is activated