Nynja Build Manual 1.4d
Figure 84 interference cure
You may experience interference between the undercarriage leg and the bolt head
as shown. If so file a rebate in the undercarraige leg as required. Make sure edges
are smooth and protect the bare metal with some paint or laquer.
4.3 Nose Gear
Refer to Figure 85.
a) If no spats are to be fitted apply grease to the inside of the nose wheel lower
and upper guides. If spats are to be fitted, then leave this until the nose leg is
removed to fit the spat.
This is to minimise the risk of contaminating the rubber washers with
grease. It is best to leave fitting the spats until the end of the build,
otherwise they are likely to suffer damage during the rest of the build
(yes you will drop that hammer on it!).
b) Slide the nose leg up through the lower guide.
c) Put a large steel washer, then 7 rubber washers, then another large steel
washer, onto the nose leg before sliding it up through the upper mount.
Washers and axle parts may be packed separately
marked ‘88’.
Check the number of rubber washers supplied, you may receive an
extra one or two. Use only the specified number.
It is important that the nose leg should be free to swivel in its guides
with little or no perceptible friction.
If the nose leg is stiff to turn due to a slight misalignment between the
upper and lower brackets try turning it around 180°.
If the nose leg still does not easily align with the upper bracket in a
side-to-side manner, slide it clear of the upper bracket and gently apply
a tweak to the lower mount using the nose leg itself as a lever. The aim
is to achieve good alignment to remove any friction in the rudder
controls. If a small tweak does not suffice, the holes securing the lower
guide may be elongated slightly, parallel with the nose leg. Do not
Summary of Contents for Nynja
Page 1: ...1 Nynja Build Manual 1 4d Nynja Build manual Version 1 4d...
Page 2: ...2 Nynja Build Manual 1 4d Figure 1 tube numbering scheme...
Page 3: ...3 Nynja Build Manual 1 4d Figure 2 Basic frame Skyranger...
Page 4: ...4 Nynja Build Manual 1 4d Figure 3 uncovered Skyranger frame...
Page 60: ...60 Nynja Build Manual 1 4d Figures 65 cable arrangement further overview...
Page 187: ...187 Nynja Build Manual 1 4d Figure 254 heavy duty power wiring schematic Rotax 912...
Page 188: ...188 Nynja Build Manual 1 4d Figure 255 low current wiring schematic Rotax 912...
Page 189: ...189 Nynja Build Manual 1 4d Figure 256 instrument wiring schematic Rotax 912...
Page 207: ...207 Nynja Build manual 1 4d 18 2 One Piece Door Figure 282 one piece door frame...
Page 269: ...269 Nynja Build manual 1 4d...
Page 270: ...270 Nynja Build manual 1 4d 27 2 Wire locking...
Page 271: ...271 Nynja Build manual 1 4d...
Page 272: ...272 Nynja Build manual 1 4d...
Page 273: ...273 Nynja Build manual 1 4d...