148
Nynja Build Manual 1.4d
Figure 183 rear overlap
e) When happy with the positioning fix first using the two bolts that connect the
TU12 tubes to their U brackets
– see fig 184 below.
Figure 184 fixing at front
f) Use 3mm plastic washers under and over the floor panel followed by a steel
penny washer before the nut on each of the forward fixing points
g) Drill and fix the rear under floor edge with Clecos/ Skinpins starting from the
middle and with spacing around 80mm.
h) Offer up the sides and mark and cut so the edge aligns neatly with the joggle
in the rear fuselage shells.
Use a Dremel cutting wheel, or a fine hacksaw blade worked at a fine angle.
Finish with a sanding block to get a nice smooth line with good alignment.
Summary of Contents for Nynja
Page 1: ...1 Nynja Build Manual 1 4d Nynja Build manual Version 1 4d...
Page 2: ...2 Nynja Build Manual 1 4d Figure 1 tube numbering scheme...
Page 3: ...3 Nynja Build Manual 1 4d Figure 2 Basic frame Skyranger...
Page 4: ...4 Nynja Build Manual 1 4d Figure 3 uncovered Skyranger frame...
Page 60: ...60 Nynja Build Manual 1 4d Figures 65 cable arrangement further overview...
Page 187: ...187 Nynja Build Manual 1 4d Figure 254 heavy duty power wiring schematic Rotax 912...
Page 188: ...188 Nynja Build Manual 1 4d Figure 255 low current wiring schematic Rotax 912...
Page 189: ...189 Nynja Build Manual 1 4d Figure 256 instrument wiring schematic Rotax 912...
Page 207: ...207 Nynja Build manual 1 4d 18 2 One Piece Door Figure 282 one piece door frame...
Page 269: ...269 Nynja Build manual 1 4d...
Page 270: ...270 Nynja Build manual 1 4d 27 2 Wire locking...
Page 271: ...271 Nynja Build manual 1 4d...
Page 272: ...272 Nynja Build manual 1 4d...
Page 273: ...273 Nynja Build manual 1 4d...