214
Nynja Build manual 1.4d
b) The frame tubes are supplied slightly over long at each end and must be
trimmed to fit.
c) Start with the lower tube first and offer it up into position.
It should be an even fit inside the opening spaced 10-15mm. make up
some spacers this size and tape them around strategically around the
opening so you can rest the tube in position and achieve this.
Figure 292 tube spacing
d) Make sure that the rear part of the door frame is close enough to the rear
cabin upright to allow the door catch to reach 5-10mm overlap with catch
plate.
Figure 293 door catch overlap
10-15mm
Summary of Contents for Nynja
Page 1: ...1 Nynja Build Manual 1 4d Nynja Build manual Version 1 4d...
Page 2: ...2 Nynja Build Manual 1 4d Figure 1 tube numbering scheme...
Page 3: ...3 Nynja Build Manual 1 4d Figure 2 Basic frame Skyranger...
Page 4: ...4 Nynja Build Manual 1 4d Figure 3 uncovered Skyranger frame...
Page 60: ...60 Nynja Build Manual 1 4d Figures 65 cable arrangement further overview...
Page 187: ...187 Nynja Build Manual 1 4d Figure 254 heavy duty power wiring schematic Rotax 912...
Page 188: ...188 Nynja Build Manual 1 4d Figure 255 low current wiring schematic Rotax 912...
Page 189: ...189 Nynja Build Manual 1 4d Figure 256 instrument wiring schematic Rotax 912...
Page 207: ...207 Nynja Build manual 1 4d 18 2 One Piece Door Figure 282 one piece door frame...
Page 269: ...269 Nynja Build manual 1 4d...
Page 270: ...270 Nynja Build manual 1 4d 27 2 Wire locking...
Page 271: ...271 Nynja Build manual 1 4d...
Page 272: ...272 Nynja Build manual 1 4d...
Page 273: ...273 Nynja Build manual 1 4d...