Diagnostics and service
5.4 Setting-up and upgrading the system
HMI Advanced (IM4)
Commissioning Manual, 03/2009, 6FC5397-0DP10-3BA0
147
5.4.3
Example: How to upgrade a PLC
Procedure
In the following example, data blocks DB3, DB67 and DB111 are not to be overwritten.
1.
As back-up, create a series commissioning archive of the PLC data.
2.
Create a descriptive file with the following contents:
;Message= designed by XXX (SIEMENS AG Erlangen)
DB3[3-78]
DB67 ; DB67 complete
DB 3 [79]
DB3[2]
DB111 ; DB111 complete
3.
Save the descriptive file as TEST1.INI and save in the directory ..\dh\arc.dir of the control
that is to be upgraded.
4.
Select the descriptive file TEST1.INI and the series commissioning archive to upgrade
the control. The syntax is checked.
5.
Press "Start": While copying, the text message is output from the INI file.
Figure 5-6
Start PLC upgrade
Summary of Contents for SINUMERIK
Page 6: ...Preface Base software and HMI Advanced 6 Commissioning Manual 03 2009 6FC5397 0DP10 3BA0 ...
Page 96: ......
Page 562: ...Index Expanding the user interface Index 4 Commissioning Manual 11 2006 6FC5397 0DP10 0BA0 ...
Page 566: ...Table of contents Online Help HE1 4 Commissioning Manual 11 2006 6FC5397 0DP10 0BA0 ...
Page 598: ...Online Help HE1 Commissioning Manual 11 2006 6FC5397 0DP10 0BA0 36 ...