Figure 3-46
Laying out and binding the PGND cable
4.
Remove the cut-off ends of the cable ties from the cabinet.
5.
Use a Phillips screwdriver to remove the M6 screw on the earthing strip of the cabinet.
6.
Use a Phillips screwdriver to fasten the other end of the PGND cable to the ground
terminal on the earthing strip.
Figure 3-47
Fastening the PGND cable
Step 3
Install power cables.
1.
Check the power supply type.
–
If the AC power supply is used, go to
.
–
If the DC power supply is used, go to
.