4.
to install the other management module (if two management modules are
required).
----End
3.8 Installing Switch Modules or Pass-Through Modules
The procedure for installing a pass-through module is the same as that for installing a switch
module.
During operations, wear protective gloves to prevent personal injury.
Procedure
Step 1
Determine the slots for installing the switch modules or pass-through modules.
A maximum of four switch modules or pass-through modules can be installed in an E9000
chassis.
shows the slot numbers of the switch modules or pass-through modules.
Figure 3-24
Slot numbers of the switch modules or pass-through modules
E9000 Server
User Guide
3 Installing the E9000
Issue 25 (2019-11-30)
Copyright © Huawei Technologies Co., Ltd.
63