6 - 20 Testing
Issue 8 January 1999
5. Repeat Steps 1 and 2 on:
a.
MCS or CCS: TB1-32 to test rectifiers 7, 8, 15, and 16
(MCS) or 13, 14, 15, and 16 (CCS).
b.
ECS-6U and ECS-12U: TB101-12 to test rectifiers 4
(8 and 12, ECS-12U).
c.
Galaxy: TB3-11 to test rectifiers 7, 8, 15, 16, 23, and
24.
Selective High
Voltage
Shutdown
(SHVSD) and
Restart
Warning
This procedure is safe only if the using equipment can tolerate
the higher voltage.
1. Using the Float Adj potentiometer, raise the rectifier
voltage to the SHVSD level of the controller.
2. Adjust the load so the rectifier delivers 20-30A, 10 to 15
percent of its rated amperage.
3. The rectifier should shut down, and the RFA LED on the
control panel should light.
4. Observe that the rectifier restarts after 4 seconds and shuts
down again. With an MCS controller, a second restart may
occur.
5. Adjust rectifier back to its proper setting. Turn the unit off,
then back on. The rectifier should restart and RFA lamp
should go off.
AC Fail Test
This test must be done on battery, with CB1 on.
1. Turn off the ac service to the rectifier. The ACF LED on
the control panel should light and an ac fail alarm should
be generated on TB3-3 and TB3-4 of CM4.
2. Restore ac to the rectifier.
Содержание Lineage 2000 J85503B-2
Страница 2: ......
Страница 4: ......
Страница 12: ...Lucent Technologies Lineage 2000 200A Ferroresonant Rectifier J85503B 2 2 List of Figures Issue 8 January 1999 ...
Страница 18: ...Lucent Technologies Lineage 2000 200A Ferroresonant Rectifier J85503B 2 1 4 Introduction Issue 8 January 1999 ...
Страница 72: ...Lucent Technologies Lineage 2000 200A Ferroresonant Rectifier J85503B 2 5 22 Installation Issue 8 January 1999 ...