Lucent Technologies Lineage
®
2000 200A Ferroresonant Rectifier J85503B-2
Issue 8 January 1999
Testing 6 - 1
6
Testing
General
This section gives test procedures for newly installed and/or
operating rectifiers. If the plant in which a rectifier is being
installed has never been operational, the plant and controller
tests must be performed before the rectifier tests. Consult the
plant and controller product manuals for their installation test
procedures.
Rectifiers can be tested on- or off-line. “On-line” means a
battery string and/or office load is connected to the rectifier. A
dummy test load is required for testing off-line, and a Battery
Plant Simulator Test Set is desirable.Without a simulator, a
minimum set of tests can be performed. See page 6-2 for a
description of the simulator and test load. For troubleshooting
and diagnostic procedures, refer to Section 7. Those unfamiliar
with the function of rectifier controls and indicators should read
Section 2.
Precautions
When working on power systems, observe safety precautions in
Section 4 and those within each procedure.
•
The ac input voltage powers certain control circuits and
relays, the front panel LEDs except ac fail, and the ac
contactor. Voltage is available to these circuits whenever
the ac service is available to the rectifier.
•
Remote sensing of rectifier output occurs via the plant
control cable connected to P5A or TB1 and TB2 on CM4.
This cable must be disconnected when internal sensing is
desired, as when testing off line using a test load.
Содержание Lineage 2000 J85503B-2
Страница 2: ......
Страница 4: ......
Страница 12: ...Lucent Technologies Lineage 2000 200A Ferroresonant Rectifier J85503B 2 2 List of Figures Issue 8 January 1999 ...
Страница 18: ...Lucent Technologies Lineage 2000 200A Ferroresonant Rectifier J85503B 2 1 4 Introduction Issue 8 January 1999 ...
Страница 72: ...Lucent Technologies Lineage 2000 200A Ferroresonant Rectifier J85503B 2 5 22 Installation Issue 8 January 1999 ...