Lucent Technologies Lineage
®
2000 200A Ferroresonant Rectifier J85503B-2
Issue 8 January 1999
Installation 5 - 1
5
Installation
General
This section outlines a sequence for installing and testing the
J85503B-2 rectifier in a battery plant. The section describes the
input and output wiring required and the recommended
procedure for installing the rectifier from uncrating through
start-up.
Preparing for
Installation
Location of the J85503B-2 rectifier and associated equipment
must conform to the specific plans of each plant installation.
Physical, thermal, and electrical characteristics are listed in
Section 2. You need to consider these characteristics when
planning any installation that includes this rectifier.
Floor Mounting
The J85503B-2 is a floor-mounted rectifier with four anchoring
holes located in the base. The rectifier must be anchored to all
types of flooring including masonry, wood, and raised floors.
Figure 5-1 is a diagram of the template, showing the anchor
holes, measurements, and instructions for drilling anchor holes
for installation in earthquake zones 3 or 4. (Anchor bolts for
Zones 0, 1, and 2 are self-drilling.) See Table 3-B for anchor bolt
ordering information. The anchor bolts are self-drilling. Figure
5-2 shows these floor anchors.
Rectifier cabinets must be aligned and shimmed to satisfy
plumbing requirements, and the floor anchors secured against
the shims. Removing the rectifier bottom-front kickplate
provides the installer with about six inches of vertical working
space in the base of the cabinet for access to the anchors.
Содержание Lineage 2000 J85503B-2
Страница 2: ......
Страница 4: ......
Страница 12: ...Lucent Technologies Lineage 2000 200A Ferroresonant Rectifier J85503B 2 2 List of Figures Issue 8 January 1999 ...
Страница 18: ...Lucent Technologies Lineage 2000 200A Ferroresonant Rectifier J85503B 2 1 4 Introduction Issue 8 January 1999 ...
Страница 72: ...Lucent Technologies Lineage 2000 200A Ferroresonant Rectifier J85503B 2 5 22 Installation Issue 8 January 1999 ...