Learning Advanced Features
Group Code
Name
LCD Display Parameter Setting
Setting range Unit
CON
77
Kinetic energy
buffering selection
KEB Select
1
Yes
0
–1
-
78
Kinetic energy
buffering start level
KEB Start
Lev
130
110
–140
%
79
Kinetic energy
buffering stop level
KEB Stop
Lev
135
115
–145
%
80
Kinetic energy
buffering slip gain
KEB Slip
Gain
300
0
–20000
-
81
Kinetic energy
buffering P-Gain
KEB P Gain 1000
0
–20000
-
82
Kinetic energy
buffering I gain
KEB I Gain
500
1
–20000
-
83
Kinetic energy
buffering
acceleration time
KEB Acc
Time
10.0 0.75~90kW
0.0
–600.0
Sec
30.0 110~500kW
Kinetic Energy Buffering Operation Setting Details
Code
Description
CON-77
KEB Select
Select the kinetic energy buffering operation when the input power is
disconnected.
Setting
Function
0
No
General deceleration is carried out until a
low voltage trip occurs.
1
Yes
The inverter power frequency is controlled
and the regeneration energy from the motor
is charged by the inverter.
CON-78
KEB Start Lev,
CON-79
KEB Stop Lev
Sets the start and stop points of the kinetic energy buffering operation.
The set values must be based on the low voltage trip level at 100%, and
the stop level (CON-79) must be set higher than the start level (CON-78).
CON-80
KEB Slip Gain
Used to prevent malfunctions caused by low voltage from initial kinetic
energy buffering occurring due to power interruptions.
CON-81
KEB P Gain
Used to maintain the voltage during the kinetic energy buffering operation.
It operates the inverter by modifying the set value to prevent malfunctions
caused by low voltage after power interruptions.
CON-82
Used to maintain the voltage during the kinetic energy buffering operation.
Summary of Contents for LSLV-H100 Series
Page 17: ...Preparing the Installation 4 37 90 kW 3 Phase ...
Page 18: ...Preparing the Installation 5 110 132 kW 3 Phase ...
Page 19: ...Preparing the Installation 6 160 185 kW 3 Phase ...
Page 20: ...Preparing the Installation 7 220 250 kW 3 Phase ...
Page 21: ...Preparing the Installation 8 315 400 kW 3 Phase ...
Page 22: ...Preparing the Installation 9 500 kW 3 Phase ...
Page 35: ...Installing the Inverter 22 ...
Page 50: ...37 Installing the Inverter Input and Output Control Terminal Block Wiring Diagram ...
Page 104: ...91 Learning Basic Features 0 10 V Input Voltage Setting Details V1 Quantizing ...
Page 181: ...168 Learning Advanced Features PID Command Block ...
Page 182: ...169 Learning Advanced Features ...
Page 183: ...170 Learning Advanced Features PID Feedback Block ...
Page 184: ...171 Learning Advanced Features PID Output Block ...
Page 185: ...172 Learning Advanced Features PID Output Mode Block ...
Page 198: ...185 Learning Advanced Features EPID1 Control block ...
Page 199: ...186 Learning Advanced Features EPID2 Control block ...
Page 220: ...207 Learning Advanced Features ...
Page 235: ...222 Learning Advanced Features The Time Chart for the Exception Day ...
Page 506: ...Table of Functions 493 ...
Page 520: ...Table of Functions 507 8 16 4 Cooling Tower MC4 Group ...
Page 549: ...Troubleshooting 536 ...
Page 569: ...Technical Specification 556 11 3 External Dimensions 0 75 30 kW 3 phase 37 90 kW 3 phase ...
Page 570: ...Technical Specification 557 110 185 kW 3 phase ...
Page 601: ...588 ...
Page 602: ...589 ...
Page 603: ...590 ...