155
Learning Advanced Features
5.6 Dwell Operation
The dwell operation is used to maintain torque during the application and release of the
mechanical brakes on lift-type loads. Inverter dwell operation is based on the Acc/Dec dwell
frequency and the dwell time set by the user. The following points also affect dwell
operation.
•
Acceleration Dwell Operation
: When an operation command runs, acceleration
continues until the acceleration dwell frequency and constant speed is reached within
the acceleration dwell operation time (Acc Dwell Time). After the Acc Dwell Time has
passed, acceleration is carried out based on the acceleration time and the operation
speed that was originally set.
•
Deceleration Dwell Operation
: When a stop command is run, deceleration continues
until the deceleration dwell frequency and constant speed are reached within the
deceleration dwell operation time (Dec Dwell Freq). After the set time has passed,
deceleration is carried out based on the deceleration time that was originally set, then
the operation stops.
Group Code Name
LCD Display Parameter Setting Setting Range
Unit
ADV
20
Dwell frequency
during acceleration
Acc Dwell
Freq
5.00
Start frequency
– Maximum
frequency
Hz
21
Operation time
during acceleration
Acc Dwell
Time
0.0
0.0
–10.0
sec
22
Dwell frequency
during deceleration
Dec Dwell
Freq
5.00
Start frequency
– Maximum
frequency
Hz
23
Operation time
during deceleration
Dec Dwell
Time
0.0
0 .0
– 60.0
sec
Note
Dwell operation does not work when:
•
Dwell operation time is set to 0 sec or dwell frequency is set to 0 Hz.
Summary of Contents for LSLV-H100 Series
Page 17: ...Preparing the Installation 4 37 90 kW 3 Phase ...
Page 18: ...Preparing the Installation 5 110 132 kW 3 Phase ...
Page 19: ...Preparing the Installation 6 160 185 kW 3 Phase ...
Page 20: ...Preparing the Installation 7 220 250 kW 3 Phase ...
Page 21: ...Preparing the Installation 8 315 400 kW 3 Phase ...
Page 22: ...Preparing the Installation 9 500 kW 3 Phase ...
Page 35: ...Installing the Inverter 22 ...
Page 50: ...37 Installing the Inverter Input and Output Control Terminal Block Wiring Diagram ...
Page 104: ...91 Learning Basic Features 0 10 V Input Voltage Setting Details V1 Quantizing ...
Page 181: ...168 Learning Advanced Features PID Command Block ...
Page 182: ...169 Learning Advanced Features ...
Page 183: ...170 Learning Advanced Features PID Feedback Block ...
Page 184: ...171 Learning Advanced Features PID Output Block ...
Page 185: ...172 Learning Advanced Features PID Output Mode Block ...
Page 198: ...185 Learning Advanced Features EPID1 Control block ...
Page 199: ...186 Learning Advanced Features EPID2 Control block ...
Page 220: ...207 Learning Advanced Features ...
Page 235: ...222 Learning Advanced Features The Time Chart for the Exception Day ...
Page 506: ...Table of Functions 493 ...
Page 520: ...Table of Functions 507 8 16 4 Cooling Tower MC4 Group ...
Page 549: ...Troubleshooting 536 ...
Page 569: ...Technical Specification 556 11 3 External Dimensions 0 75 30 kW 3 phase 37 90 kW 3 phase ...
Page 570: ...Technical Specification 557 110 185 kW 3 phase ...
Page 601: ...588 ...
Page 602: ...589 ...
Page 603: ...590 ...