10. Check the LEDs on both high-capacity AC power supply faceplates to ensure that they are operating
properly.
11. Remove the remaining two standard-capacity AC power supply from the services gateway. See
“Removing an SRX5800 Services Gateway AC Power Supply” on page 278
for instructions on removing
AC power supplies.
12. If you are upgrading to four high-capacity AC power supplies to achieve 2+2 redundancy, install
high-capacity AC power supplies in the slots you vacated in Step
. See
“Installing an SRX5800 Services
Gateway AC Power Supply” on page 281
for instructions on installing AC power supplies.
13. Check the LEDs on all installed high-capacity AC power supply faceplates to ensure that they are
operating properly.
To upgrade a services gateway that has two standard-capacity DC power supplies to two or four
high-capacity DC power supplies:
1. Ensure that the services gateway is running Junos OS Release 12.1X44-D10 or later. Earlier Junos OS
releases do not support high-capacity DC power supplies.
2. If you have not already done so, replace both standard-capacity fan trays with high-capacity fan trays.
Also replace the standard-capacity air filter with a high-capacity air filter. For more information, see
“Replacing an SRX5800 Services Gateway Fan Tray” on page 268
and
“Replacing the SRX5800 Services
Gateway Air Filter” on page 274
3. Install high-capacity DC power supplies in the two empty PEM slots in the back of the chassis. See
“Installing an SRX5800 Services Gateway DC Power Supply” on page 290
for instructions on installing
DC power supplies.
4. Check the LEDs on the faceplate of each of the new power supplies to confirm that they are operating
properly.
5. Remove both of the standard-capacity power supplies from the services gateway. See
SRX5800 Services Gateway DC Power Supply” on page 287
for instructions on removing DC power
supplies.
6. If you are installing four high-capacity DC power supply to achieve 2+2 redundancy, install high-capacity
DC power supplies in the slots vacated in Step
.
7. Check the LEDs on the faceplate of each of the new power supplies to confirm that they are operating
properly.
302
Summary of Contents for SRX 5800
Page 1: ...SRX5800 Services Gateway Hardware Guide Published 2020 02 10 ...
Page 23: ......
Page 30: ...Figure 2 Rear View of a Fully Configured AC Powered Services Gateway Chassis 31 ...
Page 111: ...LEDs 112 ...
Page 121: ...Port and Interface Numbering 122 ...
Page 127: ...Port and Interface Numbering 128 ...
Page 161: ......
Page 179: ... One SRX5K MPC IOC2 Modular Port Concentrator with two Modular Interface Cards MICs 180 ...
Page 180: ... One SRX5K 40GE SFP I O card IOC 181 ...
Page 205: ......
Page 261: ......
Page 324: ...c Upload the configuration to RE2 from the USB device 325 ...
Page 365: ...Figure 143 Installing an SPC 366 ...
Page 367: ...368 ...
Page 422: ...5 CHAPTER Troubleshooting Hardware Troubleshooting the SRX5800 425 ...
Page 423: ......
Page 457: ......
Page 473: ...475 ...
Page 476: ...Restricted Access Area Warning 478 ...
Page 483: ...485 ...
Page 496: ...Jewelry Removal Warning 498 ...
Page 499: ...Operating Temperature Warning 501 ...
Page 509: ...DC Power Disconnection Warning 511 ...
Page 513: ...DC Power Wiring Sequence Warning 515 ...
Page 516: ...DC Power Wiring Terminations Warning 518 ...
Page 519: ...DC Power Disconnection Warning 521 ...
Page 523: ...DC Power Wiring Sequence Warning 525 ...