5.6.8 Replacing the axis-6 joint unit
Location of the axis-6 joint unit
The joint unit is located as shown in the figure.
xx2000002122
Summary of the replacement procedure
This is a brief summary of the replacement procedure, containing the major actions
to be performed.
1 Remove the tool flange.
2 Remove the tool flange adapter.
3 Remove the axis-6 cover.
4 Replace the joint unit. Move the cabling from old to new joint unit.
Continues on next page
Product manual - CRB 15000
1027
3HAC077389-001 Revision: L
© Copyright 2021 - 2023 ABB. All rights reserved.
5 Repair
5.6.8 Replacing the axis-6 joint unit
Summary of Contents for CRB 15000
Page 1: ...ROBOTICS Product manual CRB 15000 ...
Page 8: ...This page is intentionally left blank ...
Page 16: ...This page is intentionally left blank ...
Page 38: ...This page is intentionally left blank ...
Page 54: ...This page is intentionally left blank ...
Page 182: ...This page is intentionally left blank ...
Page 200: ...This page is intentionally left blank ...
Page 1058: ...This page is intentionally left blank ...
Page 1076: ...This page is intentionally left blank ...
Page 1095: ......