Figure 6-296 Installing equipotential ground cables
Step 4 Install cables between the UPS and the inductor cabinet.
NO TICE
● Cables have been preinstalled and bound in the inductor cabinet.
● The cables from the inductor cabinet to the UPS are configured based on the
longest cable length before delivery. If short cables are needed in the actual
installation scenario, you can cut the excess cables and crimp terminals.
● Cables must be bound to the nearest beam or cable bridge according to the
route shown in the figure.
●
One power source
Figure 6-297 Installing cables
(1) Side view of the UPS
(2) Power cable hole
(3) Signal cable hole
UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
6 Installation