Step 7 Install mains input power cables.
Figure 6-69 Installing mains input power cables
Step 8 Install bypass input and output power cables.
●
Two power sources
Remove the copper bars between the mains and bypass input wiring
terminals.
Figure 6-70 Removing covers
Figure 6-71 Removing copper bars
a. Remove the screws that secure the guide rail of the SPD.
b. Place the SPD on the horizontal plate (without removing the cables).
c.
Remove the copper bars.
d. Reinstall the SPD.
UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
6 Installation
Issue 05 (2021-10-13)
Copyright © Huawei Technologies Co., Ltd.
127