4. Remove the bolt, spring washer, and flat washer.
NO TICE
Knock the expansion bolt into the hole until the expansion sleeve completely fits
into the hole. The expansion sleeve must be completely buried under the ground
to facilitate subsequent installation.
Figure 6-304 Drilling holes and installing expansion sleeves
(1) M12 bolt
(2) Spring washer
(3) Flat washer
(4) Expansion sleeve
(5) Expansion nut
(6) Concrete floor
Step 3 Remove the screws preinstalled on the copper bars in power cabinet 2 and store
them for future use.
Figure 6-305 Removing the preinstalled screws
Step 4 Move the cabinets to the mounting holes.
Step 5 Remove the power distribution covers from power cabinets 1 and 2.
UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
6 Installation
Issue 05 (2021-10-13)
Copyright © Huawei Technologies Co., Ltd.
259