2. Partially tighten the expansion bolt and vertically insert it into the hole. Knock
the expansion bolt using a rubber mallet until the expansion sleeve is fully
inserted into the hole.
3. Partially tighten the expansion bolt.
4. Remove the bolt, spring washer, and flat washer.
NO TICE
Knock the expansion bolt into the hole until the expansion sleeve completely fits
into the hole. The expansion sleeve must be completely buried under the ground
to facilitate subsequent installation.
Figure 6-93 Drilling holes and installing expansion sleeves
(1) M12 bolt
(2) Spring washer
(3) Flat washer
(4) Expansion sleeve
(5) Expansion nut
(6) Concrete floor
Step 3 Move the cabinets to the installation positions.
Step 4 Combine the inductor cabinet with other cabinets.
1. Remove the right panel from the UPS cabinet.
UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
6 Installation
Issue 05 (2021-10-13)
Copyright © Huawei Technologies Co., Ltd.
141