Figure 6-88 Recommended channel steel dimensions (unit: mm)
6.3.4.2 Installing Cables
Procedure
Step 1 Install cables by referring to Single UPS Installation (1200 kVA, Three-Phase
Four-Wire) > Installation in Standard Configuration > Installing Cables.
Step 2 Remove the front cover from the UPS.
Step 3 Remove an accessory cover from the top of the top air-flow cabinet.
Step 4 Connect the power cable to the 380~480V System port on the UPS and the signal
cable to the XS2 port.
Figure 6-89 Power supply to the top air-flow cabinet
----End
6.3.5 Installation in Top C Top Air-Flow Configuration
●
If both the top cabling component and the top air-flow cabinet are
configured, cabinets can be installed against a wall and cables can be routed
from the top.
UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
6 Installation
Issue 05 (2021-10-13)
Copyright © Huawei Technologies Co., Ltd.
138