Figure 6-329 Installing AC output power cables
Step 8 Install battery cables.
NO TE
● Battery cabinet connection requirements: If the UPS capacity is 800 kVA or lower,
connect battery cables only to the power cabinet on the left. If the UPS capacity exceeds
800 kVA, connect battery cables equally to both power cabinets. If the number of
battery cabinets is an odd number, the remaining battery cabinet can be connected to
any of the power cabinets.
● The figure uses the cable connection between the UPS and the SmartLi as an example.
Connect battery cables to each SmartLi.
Figure 6-330 Installing power cables between the UPS and the SmartLi
(1) Connect the ground cable of the battery string or its BBB box to the battery PE of the UPS
or the ground bar in the equipment room based on the site survey.
Step 9 Install UPS top frames (No. 14–17).
UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
6 Installation