Cisco BTS 10200 Softswitch Troubleshooting Guide, Release 5.0.x
OL-8723-19
Chapter 16 Disaster Recovery Procedures
Power Failure Recovery
Power Failure on Both Call Agent Computers
Step 1
If any platforms start, take them down first.
Step 2
Clear data directories on both sides and perform a fresh download from the EMS, as shown in the
following steps. Do the following on all platforms:
a.
Enter the following command:
cd <platform>/bin/data; rm *
b.
Restart both sides using the following command:
platform start all
c.
Do a fresh download (extract Oracle data from the EMS and send it to the Call Agent). See the
BTS
10200 Command Line Interface Guide
for the commands.
d.
Check transaction queue–make sure data is going from the EMS to the CA.
e.
Enter the command
audit db ems
to make sure everything is in sync.
Step 3
Discrepancies will have to be fixed via command line interface (CLI) commands.
Caution
This may take hours to complete and during this time, call processing is lost, that is why it is critical that
there is no common single point of failure in the power feeds.
Power Failure on Both Element Management System Computers
Step 1
If the platforms start, shut them down first.
Step 2
Audit the Oracle database.
Step 3
Check the mysql database.
Step 4
Restart both sides using the following command:
platform start all
Step 5
Enter the command
audit db ems
to make sure everything is in sync.
Step 6
Discrepancies will have to be fixed via CLI commands.
Caution
This may take hours to complete and during this time, call processing is lost, that is why it is critical that
there is no common single point of failure in the power feeds.