![Stober POSIDYN SDS 5000 Operation Manual Download Page 85](http://html.mh-extra.com/html/stober/posidyn-sds-5000/posidyn-sds-5000_operation-manual_1381280085.webp)
Integrated Bus
Operation manual POSIDYN® SDS 5000
ID 442289.06
WE
KEEP
THINGS
MOVING
85
11
11.3.2.1
Configuration of the IGB-Motionbus
During the configuration of the IGB-Motionbus, unambiguous addresses are set for the inverters and the
expected number of stations on the IGB-Motionbus.
Prerequisites:
•
You have entered all inverters which will use the IGB-Motionbus in the project.
•
The IGB-Motionbus function has been configured for all inverters.
Proceed as shown below:
Instead of using steps 2 to 6, you can also configure the IGB-Motionbus with the button
Set automatically
. In
this case, the inverters are consecutively numbered for the IGB address and the total number of stations is
entered in
A121
. If you do not get the right result, check the
Problem
column in the assistant.
How to configure the IGB-Motionbus
1. Open the assistant
Configuration IGB-Motionbus
.
The assistant indicates all inverters of the project:
Since the settings in
A120
und
A121
are not correct, the lines are highlighted in red.
2. Double click the column
A120 IGB Address
for one inverter.
3. Enter the IGB address of the inverter.
4. Double click the column
A121 IGB nominal number
for this inverter.
5. Enter the number stations expected for IGB.
6. Repeat steps 2 to 5 for each inverter which is to use the IGB-Motionbus.
The lines turn white if you have entered the values correctly:
7. Confirm the dialog screen with the
OK
button.
You have configured the IGB-Motionbus.