Parameterizing brake data
Operation manual POSIDYN® SDS 5000
ID 442289.06
WE
KEEP
THINGS
MOVING
59
7
To perform the brake test, proceed as shown below:
If you did not get the correct results, check the following:
1.
B300.2 = 1:aborted:
The
brake test
action was terminated. Reasons for the termination may include, for
example:
–
The enable was switched off during the test.
–
The enable signal has not been switched on within 30 seconds.
Perform the brake test again.
2.
B300.2 = 2:maximal torque not achieved for brake 1:
Brake 1 was unable to maintain the required torque during the test. Perform the brake grinding function
for brake 1 or replace brake 1. Then perform the brake test again.
3.
B300.2 = 3:maximal torque not achieved for brake 2:
Brake 2 was unable to maintain the required torque during the test. Perform the brake grinding function
for brake 2 or replace brake 2. Then perform the brake test again.
4.
B300.2 = 4:Error
. Reasons for the message may include:
–
No brake is parameterized. Set
F08
to
1:active
and
F09
to the brakes being used.
–
No encoder is parameterized. Determine whether an encoder exists and whether the connected motor
can be operated in control mode servo-control or vector control. Set B20 accordingly.
–
Brake test has not been activated in the device state "Ready for switch on" (e.g. in the state "Switch
on inhibit").
5.
B300.2 = 5: Encoder defective
. Reasons for the message may include:
–
The brake(s) did not release. Test the brakes.
–
The encoder is defective. Call the STOBER hotline at +49 (0) 180 5 786323.
6.
B300.2 = E62/E66 Torque limit
. Reasons for the message may include:
–
C03
/
C05
are set to low.
–
Other application-relevant torque limits are in effect.
–
The device is overloaded.
Performing a brake test
1. Change to the device state
Ready for switch on
.
2. Set parameter
B300.0
brake test & start
to
1:active
.
3. Turn on the enable signal.
The inverter starts the brake test and the motor begins rotating
4. Wait until parameter
B300.1
indicates the result 100 % and parameter
B300.2
the result
0:error free
.
5. Turn off the enable signal.
You have performed the brake test successfully.