![Rohde & Schwarz SMBV100B User Manual Download Page 930](http://html.mh-extra.com/html/rohde-and-schwarz/smbv100b/smbv100b_user-manual_1477881930.webp)
Maintenance
R&S
®
SMBV100B
928
User Manual 1178.4460.02 ─ 03
13.3
Performing Maintenance Tasks
The R&S
SMBV100B is accurate due to integrated adjustment procedures, which you
can execute directly on the instrument.
Internal Adjustments
Risk of invalid adjustment
Wait until the instrument has reached its operating temperature before you start the
adjustment procedure. The warm-up time is 30 minutes.
Self-calibration routines that require additional (external) equipment are performed at
an authorized Rohde
&
Schwarz service center.
See also
When to perform adjustments?
We recommend that you perform internal adjustments in the following cases:
●
Before starting any application, that requires a maximum of level and frequency
accuracy
●
When a long period of time has passed since the last adjustments
●
If the ambient temperature of the instrument significantly differs from the one of the
last adjustments
Additional Information to the Adjustments
During adjustments, a progress indicator shows the status of the process. If any error
occurs, the process aborts and an error message appears in the info line.
The extent of the adjustments depends on the installed options.
Performing Selftests
The available selftests check internally various functions of the instrument. We recom-
mend that you perform a selftest, if the instrument does not respond as expected.
The accessible selftests are divided in:
●
Testing baseband and BNC connections, see
Chapter 13.3.4, "Selftest Connec-
●
Testing the baseband domain, see
Chapter 13.3.5, "Selftest Baseband Settings"
●
Test generator, see
Chapter 13.3.6, "Selftest Test Generator Settings (DAC)"
Performing Maintenance Tasks