6.
A popup window indicates the test is complete. Click
OK
. The report displays on the screen.
On the report, the
Leak Rate
field on the
Instrument to Regulator Shut-off Valve -1
report
should read
Passed
. A
Passed
reading indicates the gas line from the instrument to the regulator is
clean and leak-free.
If the
Leak Rate
field indicates
Failed
, a leak is indicated between this connection. Check the
connections from the instrument to the gas regulator valve. Tighten as necessary, then run the test
again.
7.
Click the
Instrument to Gas Bottle Shut-off Valve - 2
tab to display its report.
Summary of Contents for Gemini VII 2390a
Page 1: ...Gemini VII Operator s Manual V3 02 239 42828 01 Jan 2014...
Page 4: ......
Page 12: ...Table of Contents Gemini VII viii 239 42828 01 Nov 2013...
Page 36: ...Menu Structure Gemini VII 2 14 239 42828 01 Dec 2012...
Page 192: ...Service Test Gemini VII 6 24 239 42828 01 Dec 2012...
Page 217: ...Gemini VII Report Examples 239 42828 01 Dec 2012 7 25 Isotherm Linear Plot...
Page 218: ...Report Examples Gemini VII 7 26 239 42828 01 Dec 2012 BET Surface Area Report...
Page 219: ...Gemini VII Report Examples 239 42828 01 Dec 2012 7 27 BET Surface Area Plot...
Page 220: ...Report Examples Gemini VII 7 28 239 42828 01 Dec 2012 t Plot...
Page 221: ...Gemini VII Report Examples 239 42828 01 Dec 2012 7 29 BJH Adsorption Cumulative Pore Volume...
Page 222: ...Report Examples Gemini VII 7 30 239 42828 01 Dec 2012 BJH Adsorption dV dlog w Pore Volume...
Page 264: ......
Page 266: ......
Page 294: ...Appendix B Gemini VII B 28 239 42828 01 Nov 2013...
Page 364: ...Appendix F Gemini VII F 18 239 42828 01 Dec 2012...
Page 372: ...Gemini VII Smart VacPrep Operator Manual Dec 2013 G 1 G Smart VacPrep Operator Manual...
Page 380: ...Contact Us vi Smart VacPrep Operator Manual...
Page 390: ...2 About the Software 2 4 Smart VacPrep Operator Manual...
Page 424: ...8 Error Messages 8 4 Smart VacPrep Operator Manual...