6.2 Initial commissioning of the drive system
Make sure that external pulse enabling is inhibited before starting initial commissioning in order to
avoid uncontrolled starting of the motor.
It is assumed that the individual controllers are set to default values which guarantee a perhaps not
optimum, but controlled operation of the motor.
Subsequently the following parameters should be set or their values checked:
The description of the operation software is covered in a separate operation manual.
PC
unit
Summary of Contents for BUS 6-T Series
Page 6: ...Abbreviations IV Controller BUS 6 T 5 94017 06 Baumüller Nürnberg GmbH ...
Page 10: ...Technical data 4 Controller BUS 6 T 5 94017 06 Baumüller Nürnberg GmbH ...
Page 18: ...Assembly 12 Controller BUS 6 T 5 94017 06 Baumüller Nürnberg GmbH ...
Page 22: ...Installation 16 Controller BUS 6 T 5 94017 06 Baumüller Nürnberg GmbH ...
Page 40: ...Commissioning 34 Controller BUS 6 T 5 94017 06 Baumüller Nürnberg GmbH ...
Page 52: ...Commissioning Torque control 46 Controller BUS 6 T 5 94017 06 Baumüller Nürnberg GmbH PC unit ...