24
a.
When the width of angle steel is less than 60 mm or equal, do not consider avoiding.
b.
When the width of angle steel is more than 60 mm, it is interfering with the holes
which routing cables, please cut out holes to avoid interfering.
2.
In the top of the bracket is attached shock pad which is made of
Ethylene-Propylene-Diene Monomer (EPDM), and the thickness is 5 mm.
3.
Please note that to control the welding process and avoid excessive error.
4.
Adjust the height of the support according to the actual situation.
3.1.3 Installation Precautions
Before installing the NetCol5000-A020, read this section carefully and perform installation by
strictly following the guidance in this section.
Precautions
Before installation, check that the environment meets the requirements, and check
whether reconstruction is needed for routing pipes and cables and constructing
ventilation pipes.
Install the NetCol5000-A020 according to the design drawing and reserve space for
maintenance. Ensure that a minimum of 1000 mm maintenance clearance is reserved in
either front or rear of the indoor unit. If a maintenance clearance of 1000 mm is reserved
on a side of the indoor unit, ensure that a minimum of 600 mm maintenance clearance is
reserved on the other side, as shown in
Figure 3-6
.
Figure 3-6
Maintenance space requirements (unit: mm)
(1) NetCol5000-A020
(2) Equipment
The shelter should have good heat insulation, and the walls and floor should be protected
against moisture.