4 Power-On Commissioning
Issue 01 (2014-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
66
Figure 4-3
Removing cables from the compressor
Procedure
Step 1
Check that the water inlet pipes and drainpipes of the humidifier are properly connected and
outer thermal insulation foam is reliably fixed.
Step 2
Check that the phase sequence of L1/L2/L3/N/PE cables to the indoor and outdoor units is
correct. For details, see
3.8.2 Connecting Power Cables
and
NetCol500 Outdoor Unit User
Manual
.
Step 3
Check that the voltage distributor is properly connected. For details, see
3.8.3 Installing the
Voltage Jumper
.
Step 4
Check that signal cables to the indoor and outdoor units are properly connected. For details,
see
3.8.4.1 Preparations Before Connection
.
Step 5
Check that the water leakage sensor is installed into position. For details, see
3.8.4.3
Connecting a Water Sensor
.
Step 6
If group control networking is deployed, check that cables are correctly connected and DIP
switches on the main control board are set properly. For details, see
3.8.5 Teamwork
Networking and Monitoring
.
Step 7
Check that cables to the ambient temperature and humidity sensor are correctly connected and
related DIP switches are set properly. For details, see
3.8.6 Installing T/H Sensors
.
Step 8
Check that refrigerant is charged in to the cooling system, pipelines to the humidifier cylinder
are properly connected, and the manual drainage button on one side of the electrical control
box is set to "O".
----End