NetCol5000-A020 Air Cooled In-row Precision Air
Conditioner
User Manual
4 Power-On Commissioning
Issue 01 (2014-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
71
4.6 Powering off the Equipment
Procedure
Step 1
On the main menu, tap
Shutdown
.
Exercise cautions when performing operations on the equipment because the equipment is
under power.
Step 2
Switch off the front end circuit breaker and the main circuit breaker QF1.
You must switch off the front end circuit breaker when replace or maintain the air
conditioner components.
Only switch off the main circuit breaker QF1 when check whether the power-off function
is normal.
Step 3
Install the air filters and the rear door.
----End