3.8.4.3 Connecting a Water Sensor
Context
Place the water sensor with the sheet metal upwards and detection board downwards.
Procedure
Step 1
Connect one end of the signal cables to a water sensor.
Step 2
Connect the other end of the signal cables to terminals 09 and 10 on the X106 terminal block
of the electrical control box.
Figure 3-31
shows the location of the water sensor.
Step 3
Use a cable tie to fix the cables on the cabinet.
----End
3.8.5 Teamwork Networking and Monitoring
To implement teamwork networking and monitoring, you need to connect communications
cables and set the DIP switch on the main control board.
Context
J73 teamwork networking ports J73UP and J73DOWN (as shown in
Figure 3-27
) on one side
of the electrical control box enable CAN group control networking communication between
cooling products, and communication between cooling products and the customer monitoring
system connecting over the RS485 bus.