Scalar i6000 Installation Guide
309
Installation Verification Test Overview
The installation verification test enables you to verify that the library’s installation and configuration is
complete and functioning correctly. The installation verification test runs the following individual tests:
•
Library alignment test
•
Picker assembly test
•
I/E station assembly test
•
Get/Put test
•
Scanner fiducial test
These tests require that you log on as an admin or service user. The accessor assembly must be ready and
functional, and the library must be powered on. In addition, the library must be in an offline state, and at
least one scratch tape must be inserted in the I/E station.
The smaller library configuration will require about 1 hour and the larger configurations will require as long
as 4 hours to run the installation verification test. The time to complete individual tests on an twelve module
configuration is approximately:
•
Library alignment test - 45 minutes
•
Picker assembly test - 4 minute
•
I/E station assembly test - 7 minutes for each I/E station
•
Get/Put test - 2 hours and 45 minutes
•
Scanner fiducial test - 75 minutes
Note
These times do not include debug or repair time.
Summary of Contents for Scalar i6000
Page 20: ...8 About This Guide and Your Product...
Page 38: ...26 Installing a Stand Alone Control Module...
Page 104: ...92 Installing a Multi Module Library...
Page 156: ...144 Installing Cartridges...
Page 164: ...152 Setting up Your Library for Access...
Page 242: ...230 Configuring the Library...
Page 304: ...292 Adding Optional Hardware eight 2 5 mm screws...
Page 318: ...306 Adding Optional Hardware...
Page 336: ...324 Installation Testing and Verification Figure 35 Example Test Log Output...
Page 356: ...344 Testing and Calibrating the Digital Level...
Page 362: ...350 LBX Board and Terminator...
Page 380: ...368 Glossary...
Page 384: ...372 Index...