Installation
56
RT-SVX24J-EN
Air-Cooled and Evaporative Condensers—
Two-Piece Unit Fit Up
1.
Rig the low side unit (Air handler) and the high side unit
(Condenser) separately.
2. First, rig and set the low side unit on the roof curb
(aligned with return end).
3. Take off and discard the protection boxes. (Do not
remove wire shields).
4. Remove the rail connector splice brackets and install
the brackets on the low side unit base rails.
5. Take off the side panels (these are labeled) and the top
cover of the high side unit and set aside to be
assembled later.
6. Rig and set the high side unit on roof curb pedestal,
using the rail splice bracket as an alignment aid to
connect the Low and high side units.The Low and high
side unit rails should be butted together with a
maximum 2" separation.
7.
Remove the left upper and lower louvered panels and
the corner panels on each side to aid in tubing and
wiring connections.
Figure 32. Roof panel splice plate connection
Figure 33. Side panel and roofcap reinstallation
Apply s plice plate to
bottom of roof
panels at unit split
Reinstall side
panels removed
earlier
Reinstall roof cap
removed earlier
Apply butyl tape
on unit split in roof
Figure 34. (1) Protection box removal/(2) rail connector
installation position
Note: Do not remove the
wiring shields
(2)
Note: Unscrew the rail connector
as shown in fig 1(b) and screw
back to these locations
(1)
(a)
(b)
Rail connector
shipping position
Содержание SEHJ090-162
Страница 40: ...Dimensional Data 40 RT SVX24J EN Figure 13 Evaporative condenser water connection locations RIGHT SIDE VIEW ...
Страница 48: ...Installation 48 RT SVX24J EN Figure 18 Ductwork conversion ...
Страница 58: ...Installation 58 RT SVX24J EN Figure 36 5 Connected tubes 6 install panels Connected tubes 5 6 ...
Страница 75: ...Installation RT SVX24J EN 75 Figure 51 Hot water coil piping Figure 52 Steam coil piping ...
Страница 87: ...Installation RT SVX24J EN 87 Figure 57 Typical field wiring diagram for 90 to 162 ton CV control options ...
Страница 89: ...Installation RT SVX24J EN 89 Figure 59 Typical field wiring diagram for 90 to 162 ton VAV control options ...