Unit Startup
172
RT-SVX24J-EN
30. Gas heat condensate line + heat tape installed where applicable
Where applicable: HW/Steam Heat
31. Modulating valve and actuator (HW and Steam) installed/wired
32. Steam heat swing check vacuum breakers installed per IOM direction
33. Steam heat condensate trap provided
34. O/A pressure sensor installed and piped
35. High side to low side piping to be completed prior to Trane technician arriving for startup
36. Space sensor and pneumatic tubing installed properly
Complete
37.
Compressor discharge service valves, oil valves and liquid lines valves open/back seated (excludes Schrader valves)
38. Compressor oil levels (½ -¾ high in glass) proper
39. Verify power wires are connected in the high voltage power box
40. Verify field installed control wiring landed on correct terminals
41. All fan belts tensioned and bearings greased
42. Heat wheel rotates freely by hand
43. Reenergize power. Phase sequence (A-B-C) proper for compressor rotation
44. Incoming voltage balanced
45. All panels/doors secured prior to startup
Start unit
46. Service test guide used to operate unit components
47.
Fan amperages within nameplate specs
48. Verify system airflow
49. Dampers open and close properly
50. Adjust outside air damper travel
51. On evaporative condenser models: Verify the sump fills to within 1.5” below the overflow, which is within the slot on the max float
bracket (see
Figure 114, p. 162
)
52. Compressor operation normal and within amperage rating
53. Superheat (14-18°F) and subcooling (14-22°F) normal for air-cooled units
54. Electric, hot water and steam heating operation checked
55. Gas heating startup sequence of operation per IOM has been followed
56. Gas heat operation has been verified with combustion analyzer
57.
Incoming gas pressure does not drop below 7" water column when burner is on high fire
58. Operating log completed
Table 49.
Trane startup checklist (continued)
Содержание SEHJ090-162
Страница 40: ...Dimensional Data 40 RT SVX24J EN Figure 13 Evaporative condenser water connection locations RIGHT SIDE VIEW ...
Страница 48: ...Installation 48 RT SVX24J EN Figure 18 Ductwork conversion ...
Страница 58: ...Installation 58 RT SVX24J EN Figure 36 5 Connected tubes 6 install panels Connected tubes 5 6 ...
Страница 75: ...Installation RT SVX24J EN 75 Figure 51 Hot water coil piping Figure 52 Steam coil piping ...
Страница 87: ...Installation RT SVX24J EN 87 Figure 57 Typical field wiring diagram for 90 to 162 ton CV control options ...
Страница 89: ...Installation RT SVX24J EN 89 Figure 59 Typical field wiring diagram for 90 to 162 ton VAV control options ...