Unit Startup
156
RT-SVX24J-EN
Outer or Satellite Segment Replacement
1.
Disconnect all electrical power.
2. Secure wheel from rotation.
3. Rotate out the two segment retainer latches, one for
each side of the selected segment opening, such that
they are 90° from the wheel rim. See
Figure 108, p. 155
.
4. Set the segment in the gap between the segment
retainer latches, pressing it toward the center of the
wheel and inward against the spoke flanges. See
Figure 111, p. 158
. If hand pressure does not fully seat
the segment, insert the flat tip of a screwdriver
between the wheel rim and the outer corners of the
segment and apply gentle force while guiding the
segment into place. Be careful not to bend the wheel
frame or the segment frame with the screwdriver.
5. Reinstall forked segment retainer(s)
Note:
Only applies when there is an adjacent segment in
place.
6. Close each segment retainer latch under the segment
retaining catch.
7.
Rotate the wheel and repeat this sequence with the
remaining segments.
Removing and replacing the segments with a spare set can
be accomplished more quickly. Remove the dirty segment,
replace it with a clean segment, then move to the next
segment.
Filtration
Galvanized steel permanent filters are provided to prevent
debris from entering the energy wheel section.The return
air filters are mounted in a filter rack underneath the
energy recovery wheel, and are accessible from either side
by means of the double access doors.The outside air filter
rack is attached to the energy recovery cassette. Use the
unit filter / evaporator coil access doors to service the
energy recovery outside air filters.
1.
Disconnect all electrical power.
2. Remove all filter media from the vertical filter rack
providing air filtration for the unit evaporator coil.
3. Remove the sheet metal screws in the hinged access
panel beneath the bypass damper assembly.
4. Rotate the access panel downwards.
5. Reach in past the damper wall to access the flexible
filter puller(s). Pull them towards the evaporator coil
enough to reach the second filter in each slot of the
filter rack. Refer to
Table 45, p. 156
for filter
information.
Note:
Inspect these filters monthly and clean them as
necessary.
Bearing and Motor Lubrication
The wheel drive motor and wheel support shaft bearings
are permanently lubricated and no further lubrication is
necessary.
Service and Repair
Drive Belt Replacement
The drive belt is a urethane stretch belt designed to
provide constant tension throughout the life of the belt. No
WARNING
Hazardous Voltage!
Disconnect all electric power, including remote
disconnects before servicing. Follow proper lockout/
tagout procedures to ensure the power can not be
inadvertently energized. Do not open the service access
doors while the unit is operating. Failure to disconnect
power before servicing could result in death or serious
injury.
WARNING
Rotating Components!
The following procedure involves working with
rotating components. Disconnect all electric power,
including remote disconnects before servicing. Follow
proper lockout/tagout procedures to ensure the power
can not be inadvertently energized. Failure to
disconnect power before servicing could result in
rotating components cutting and slashing technician
which could result in death or serious injury.
WARNING
Hazardous Voltage!
Disconnect all electric power, including remote
disconnects before servicing. Follow proper lockout/
tagout procedures to ensure the power can not be
inadvertently energized. Do not open the service
access doors while the unit is operating. Failure to
disconnect power before servicing could result in death
or serious injury.
Table 45. ERW Filter Information
Galvanized
Steel Filter
Information
90-118T
Low CFM
ERW
Units (in.)
90-162T
Low CFM
ERW
Units (in.)
90-162T
Standard CFM
ERW
Units (in.)
RA Filters (size,
number)
24x24x1, 10
24x24x1, 10
24x24x1, 10
FA Filters (size,
number
224x24x1, 8
24x24x1, 6
24x24x1, 8
12x24x1, 2
Содержание SEHJ090-162
Страница 40: ...Dimensional Data 40 RT SVX24J EN Figure 13 Evaporative condenser water connection locations RIGHT SIDE VIEW ...
Страница 48: ...Installation 48 RT SVX24J EN Figure 18 Ductwork conversion ...
Страница 58: ...Installation 58 RT SVX24J EN Figure 36 5 Connected tubes 6 install panels Connected tubes 5 6 ...
Страница 75: ...Installation RT SVX24J EN 75 Figure 51 Hot water coil piping Figure 52 Steam coil piping ...
Страница 87: ...Installation RT SVX24J EN 87 Figure 57 Typical field wiring diagram for 90 to 162 ton CV control options ...
Страница 89: ...Installation RT SVX24J EN 89 Figure 59 Typical field wiring diagram for 90 to 162 ton VAV control options ...