7. Fieldbus Device Commissioning
This section outlines a typical process to follow to commission a fieldbus loop in an
Experion system. This section does not provide detailed procedures for each stage in the
process. Please reference appropriate sections in this document or applicable vendor
documentation for detailed information, if required.
The following table lists the topics included in this section. If you are viewing this
information online, just click the topic title to jump to the information location.
Topic
Getting Started
Connecting Devices
Checking Device
Checking Control Strategy
Flowchart Summary
7.1 Getting
Started
Read this first
The CIOM-A Fieldbus Interface Module (FIM) sets many parameters within a fieldbus
device during its initial setup and commissioning in an Experion system. While you can
change some parameters, such as calibration ones, when the device is being operated on a
workbench or at a location apart from the system, you must
not
change certain other
parameters. The following table outlines the functions you must consider before
commissioning a device.
For This Function. . .
Consider This . . .
Содержание Experion PKS Series A
Страница 241: ...5 Configuration 5 9 Summary R400 Experion PKS Series A Fieldbus Interface Module User s Guide 241 July 2010 Honeywell ...
Страница 242: ......
Страница 559: ......
Страница 560: ...Honeywell Process Solutions 1860 W Rose Garden Lane Phoenix AZ 85027 USA ...