8-14
MM2 Motor Manager 2
GE Power Management
8.5 CHASSIS MOUNT UNITS
8 MM2PC
®
SOFTWARE
8
3. Select the Communication > Troubleshooting menu. This opens the Memory Map Inspection
window shown below:
4. Type 1139 (the address of baud rate setpoint) in the address box and 4 (4 = 19200 baud) in the
values box in the Memory Map Insertion section. Refer to Section 6.5: MEMORY MAP on page
6–19 for details.
5. Click Send and then Yes to confirm the setpoint write action. All communications will immediately
be lost – ignore any errors.
6. Select OK to exit the Troubleshooting window.
7. Select the Communication > Computer menu item.
8. Change the baud rate setting to 19200, click Store, then click OK. Select the Communication >
Computer menu item again and click ON in the Communication Control section. The status
should now read “Program is now talking to Multilin device.”
9. Select OK to exit the Communication/Computer window and select the Communication > Trou-
bleshooting menu item.
10. Enter 1147 (address of the parity setpoint) in the address box and 1 (1 = even) in the values box
in the Memory Map Insertion section. Refer to Section 6.5: MEMORY MAP on page 6–19 for
details.
11. Click Send and then Yes to confirm the setpoint write action. All communications will immediately
be lost – ignore any errors.
12. Select OK to exit the Troubleshooting window.
13. Select the Communication > Computer menu item.
14. Change the parity setting to even, click Store, then click OK. Select the Communication >
Computer menu item again and click ON in the Communication Control section. The status
should now read “Program is now talking to Multilin device.”
15. Select OK to exit the Communication/Computer window.
Содержание MOTOR MANAGER 2
Страница 2: ......
Страница 4: ......
Страница 21: ...GE Power Management MM2 Motor Manager 2 2 3 2 INSTALLATION 2 1 MOUNTING 2 Figure 2 4 TYPICAL WIRING DIAGRAM ...
Страница 33: ...GE Power Management MM2 Motor Manager 2 3 7 3 HARDWARE 3 3 THEORY OF OPERATION 3 Figure 3 2 BLOCK DIAGRAM ...
Страница 34: ...3 8 MM2 Motor Manager 2 GE Power Management 3 3 THEORY OF OPERATION 3 HARDWARE 3 ...
Страница 80: ...5 12 MM2 Motor Manager 2 GE Power Management 5 5 A4 STATISTICS 5 ACTUAL VALUES 5 ...
Страница 130: ...7 2 MM2 Motor Manager 2 GE Power Management 7 1 INJECTION TESTING 7 TESTING 7 Figure 7 1 SECONDARY INJECTION TEST SETUP ...
Страница 153: ...GE Power Management MM2 Motor Manager 2 9 5 9 STARTER TYPES 9 2 FV REVERSING STARTER 9 Figure 9 4 FV REVERSING STARTER ...
Страница 161: ...GE Power Management MM2 Motor Manager 2 9 13 9 STARTER TYPES 9 4 SLIP RING STARTER 9 Figure 9 10 SLIP RING STARTER ...
Страница 187: ...GE Power Management MM2 Motor Manager 2 9 39 9 STARTER TYPES 9 13 SOFT STARTER 9 Figure 9 25 SOFT STARTER ...
Страница 188: ...9 40 MM2 Motor Manager 2 GE Power Management 9 13 SOFT STARTER 9 STARTER TYPES 9 ...
Страница 212: ...E 4 MM2 Motor Manager 2 GE Power Management E 1 CT ISOLATION APPENDIXE E ...
Страница 220: ...iv MM2 Motor Manager 2 GE Power Management INDEX ...