SVS/12
120
994.530 G01 02
C
HANGING A
10/12
K
V
BOTTOM CONTACT WITH
SPACER FOR A
20/24
K
V-
BOTTOM CONTACT
,
630
A
1. Remove the high-voltage fuses according to the
procedure described in chapter 4.3.6.
In this situation the disconnector is in the earthing
position and the load-break switch cannot be turned on.
2. Switch the low-voltage side of the transformer off and
check - before removing the bottom contact with spacer
- that the outgoing cables are not live.
3. Remove the 10/12 kV bottom contacts and the spacers
using the special spanner.
4. Clean the contact surfaces of the 20/24 kV bottom
contacts with, for example, Scotch-Brite scouring pads.
5. Fit the preassembled 20/24 kV bottom contact using
the special spanner set to a tightening torque of 20 Nm,
as follows:
Fit the preassembled 20/24 kV bottom contact on
the spanner.
Rest the contact against the side of the fuse holder
and slowly lower the whole assembly.
4. Removing bottom contact 10/12 kV with spacer
6. Fit the 20/24 kV fuses and turn on the load-break
switch (see chapter 4.3.6).
Summary of Contents for SVS/12
Page 133: ...SVS 12 994 530 G01 02 133 9 2 Voltage detecting system Wega 1 2...
Page 134: ...SVS 12 134 994 530 G01 02...
Page 135: ...SVS 12 994 530 G01 02 135...
Page 136: ...SVS 12 136 994 530 G01 02...
Page 137: ...SVS 12 994 530 G01 02 137 9 3 Phase monitor Orion 3 0...
Page 138: ...SVS 12 138 994 530 G01 02...