994.530 G01 02
7. Replace the fuse in the handle.
Inserting the fuse in the 12 kV handle
W
ARNING
When fitting the fuse, do not rest the handle
against the wall or the ground, to avoid
damaging the fuse internals. Fit the fuse with the
striker pin output in the handle.
8. Slide the handle with the fuse into the installation.
Inserting the 12 kV fuse with handle
9. Close the protection cover by pushing the selector (7)
up and turning the key a quarter turn clockwise.
10. Set the disconnector to the busbar position (see
chapter 4.2.4).
11. Switch the load-break switch/fuse panel on (see
chapter 4.2.2).
Inserting the fuse in the 12 - 24 kV handle
N
OTE
On a 12 - 24 kV version, when removing the fuse
from the handle, the ring of the handle must first
be pushed backwards.
Fitting the 12 - 24 kV fuse with handle
Summary of Contents for SVS/12
Page 133: ...SVS 12 994 530 G01 02 133 9 2 Voltage detecting system Wega 1 2...
Page 134: ...SVS 12 134 994 530 G01 02...
Page 135: ...SVS 12 994 530 G01 02 135...
Page 136: ...SVS 12 136 994 530 G01 02...
Page 137: ...SVS 12 994 530 G01 02 137 9 3 Phase monitor Orion 3 0...
Page 138: ...SVS 12 138 994 530 G01 02...