SVS/12
994.530 G01 02
43
9. Then fasten the cable from above (torque 15 Nm) with
the hexagon socket screw M8 x 25 (with conical spring
washer and plain washer).
N
OTE
If the connection is not pressed fully against the
contact face, the cable core may be damaged
when the hexagon socket screw is tightened.
This situation must be avoided.
10. Seal the non-cable side as follows:
Place the sleeve with the sealing cap in the opening
of the cable connection.
During this operation, hold a nylon vent thread
between the sleeve and the moulded resin, and
afterwards pull this thread out.
(figure 7).
N
OTE
These sleeves are always coded as sleeve no. 1.
The other sleeves for the cable connection have
a different code, depending on the cable to be
connected.
11. Fasten the cable to the frame with the wooden terminal
block or with a cable clamp (figure 8).
Ensure that the bending radius of the cable is at least
that specified by the supplier.
For Eaton transformer cables, the bending radius is 15
times the external diameter of the cable.
12. Earth the screening of the cables to the earth bar via
the flexible earth connection.
13. Place the grommet in the floor plate of the panel.
6.
7.
8.
Hout en klemblok
Wooden terminal block
Summary of Contents for SVS/12
Page 133: ...SVS 12 994 530 G01 02 133 9 2 Voltage detecting system Wega 1 2...
Page 134: ...SVS 12 134 994 530 G01 02...
Page 135: ...SVS 12 994 530 G01 02 135...
Page 136: ...SVS 12 136 994 530 G01 02...
Page 137: ...SVS 12 994 530 G01 02 137 9 3 Phase monitor Orion 3 0...
Page 138: ...SVS 12 138 994 530 G01 02...