SVS/12
118
994.530 G01 02
6.1.3
Topping up grease-filled cable boxes,
630 A panels
Supplied accessories
Filling device
L
IFE HAZARD
!
When performing work on the cable box, the
relevant cable(s) must always be earthed.
1. Check the cable grease level using a lamp, if
necessary.
Once the grease level has dropped to a point below
the cable core clamps, because grease has been
absorbed by the cable, the cable box must be
topped up.
In this case, the hose of the filling device - prior to
being inserted into the cable box
– must be entirely
filled with grease so as to prevent the ingress of air.
For filling the cable box, see also chapter 3.3.8.
2. Undo the hose clip and slide the cable box so far down
that the nylon vent threads can be fitted (see figure 1):
If it is difficult to slide down because the grease has
become too viscous, you may heat the cable box a
little, using a hair drier for instance.
D
ANGER WARNING
Never heat the cable box with a naked flame.
6.1.4
Cleaning the installation
If the installation has been set up in accordance with the
guidelines described in chapter 3.1, cleaning is not
necessary.
For installations that are dirty, the following measures are
required:
L
IFE HAZARD
!
The installation must be made completely dead.
1.
Clean dirty parts with a damp cloth.
Dry the installation and lightly grease it with silicone
grease, type DC-4 or MAC 05. Polish the film of grease
until a polished, non-sticky finish is obtained.
N
OTE
MAC 05 is a cleaning and conditioning agent
developed by Eaton which gets rid of surface
dirt and creates a moisture-repellent film of
silicone on the moulded resin.
Summary of Contents for SVS/12
Page 133: ...SVS 12 994 530 G01 02 133 9 2 Voltage detecting system Wega 1 2...
Page 134: ...SVS 12 134 994 530 G01 02...
Page 135: ...SVS 12 994 530 G01 02 135...
Page 136: ...SVS 12 136 994 530 G01 02...
Page 137: ...SVS 12 994 530 G01 02 137 9 3 Phase monitor Orion 3 0...
Page 138: ...SVS 12 138 994 530 G01 02...