1.3 Safety instructions
1.3.1
Applicable regulations
SVS/12 switchgear is designed in compliance with EU
safety directives.
SVS/12 switchgear satisfies:
IEC 62271-1
Common specifications for high voltage
switchgear and controlgear standards
(prHD448), for the general regulations.
IEC 60265-1
High voltage switches for rated voltages
above 1 kV and less than 52 kV
(HD355.1), as a load break switch
combination for general use.
IEC 62271-105
High voltage alternating current switch
fuse combinations (prEN62271-105), as a
load-break switch with fuses.
IEC 62271-100
High voltage alternating current circuit
breakers (prHD348), as a circuit-breaker.
IEC 62271-200 Alternating current metal enclosed
switchgear and controlgear for rated
voltages above 1 kV and up to and
including 52 kV (EN 62271-200), in the
"compartmented" version based on the
insulated connections method.
1.3.2
Safety measures
Safety measures are a combination of the safety aspects
incorporated into the design of the system, and the
precautions to be taken before and during use.
A.
D
ESIGN
A number of aspects are mentioned below. These are
explained in chapters 1.1 and 4.1.
A.1 Safe
Earthed metal enclosure and full primary insulation
protect against electric shock
Mechanical interlocks prevent unauthorised switching
operations.
Continuous voltage indication
Mechanical interlocks protect access to the cable
connections for changing fuses and floor contacts
Environment-friendly materials
A.2 User-friendly
Uniform and simple control panels
Easy access to the cable connection
Sufficient space for cable termination
Easy to transport
Easy to install in the operating area
B.
U
SE
This includes aspects relating to:
switchroom
personnel
execution of work
fire-fighting
B.1 Switchroom
For the construction and related aspects of switchrooms,
local regulations must be complied with.
Eaton also gives the following advice with regard to clear
spaces, escape routes and entrances:
Clear space
In front of switchgear installations or between two facing
switchgear installations there must be a clear space along
the whole length. This clear space must not be less than
1.25 m in front of the installation (1.75 m for a face-to-face
arrangement).
For the height, a clear space of at least 2 m is required
from the floor or the platform in front of the installation.
Escape routes
In front of switchgear installations or between two facing
switchgear installations there must be an escape route at
least 0.5 m wide and 2 m high along the whole length.
Escape routes must be in a straight line as far as possible.
There must be no projecting parts within these escape
routes.
The height must be measured from the floor or from the
platform in front of the switchgear.
Dimensions
For the dimensions of the SVS/12 system, see chapter 2.3.
Summary of Contents for SVS/12
Page 133: ...SVS 12 994 530 G01 02 133 9 2 Voltage detecting system Wega 1 2...
Page 134: ...SVS 12 134 994 530 G01 02...
Page 135: ...SVS 12 994 530 G01 02 135...
Page 136: ...SVS 12 136 994 530 G01 02...
Page 137: ...SVS 12 994 530 G01 02 137 9 3 Phase monitor Orion 3 0...
Page 138: ...SVS 12 138 994 530 G01 02...