Protective Elements
Zone Coordination
General Description
What does Zone Coordination mean?
Zone Coordination means, that the upstream protection device is doing a virtual autoreclosure while the
downstream protective device is doing a “real” autoreclosure. By means of the zone coordination selectivity can be
kept, even if a downstream protective device changes its tripping characteristic after a reclosure cycle. The virtual
autoreclosure of the upstream device follows the downstream autoreclosure.
What application can be realized by means of Zone Coordination?
A radial distribution system is protected by an upstream protective device (with a circuit breaker) and a downstream
protective device with a reclosure and fuse. By means of the zone coordination a “fuse saving scheme” might be
realised. In order to “save fuses” the downstream protective device might trip for the first reclosure attempt at low
tripping values (undergrade the fuse, trying to avoid a damaging of the fuse). If the reclosure attempt fails the
tripping values might be risen (overgrade the fuse) for the second reclosure attempt (using higher tripping
values/characteristics).
What is essential?
The triggering thresholds of the upstream and the downstream devices have to be the same but the tripping times
have to be selectively.
How is Zone Coordination activated?
The zone coordination function is part of the autoreclosure element and it can be enabled by setting the parameter
»
Zone coordination« as »active« within the menu [Protection Para/AR/General Settings] for an upstream feeder
protection device.
How does the Zone Coordination work (within the upstream protection device)?
When the zone coordination function is enabled, it works similar to a normal autoreclose function with the same
setting parameters: maximum reclosure attempts, dead timer for each shot, initiate functions for each shot and
other timers for autoreclose process, but with the following zone coordination features to coordinate with the
downstream reclosers:
The corresponding dead timer for each shot will be started even the breaker of the upstream feeder relay is NOT
tripped from the assigned initiate protective functions.
The dead timer begins timing once the autoreclose senses a drawback of the assigned overcurrent protection
pickup signal. This exhibits that the fault current was tripped by the downstream recloser opening.
The shot counter of an enabled zone coordination will be incremented after the dead timer elapses, even there is
no breaker reclosing command issued and meanwhile the »
T
-R
UN
2R
EADY
« timer is started.
If a permanent fault exists after the downstream recloser is reclosed, the fault current makes the upstream
overcurrent protection picks up again, but with the pickup thresholds or operating curves controlled by the
incremented shot number. In this way, the upstream feeder will “follow” the protective settings of downstream
recloser shot by shot.
795
MCDLV4
DOK-HB-MCDLV4-2E
Содержание HighPROtec MCDLV4
Страница 1: ...Manual Line Differential Protection MCDLV4 Software Version 3 4 a DOK HB MCDLV4 2E Revision A English...
Страница 3: ...Order Code Order Code 3 MCDLV4 DOK HB MCDLV4 2E...
Страница 47: ...Installation and Connection 47 MCDLV4 DOK HB MCDLV4 2E...
Страница 164: ...Input Output and LED Settings 164 MCDLV4 DOK HB MCDLV4 2E...
Страница 433: ...Parameters 433 MCDLV4 DOK HB MCDLV4 2E...
Страница 457: ...Device Parameters 457 MCDLV4 DOK HB MCDLV4 2E...
Страница 473: ...Blockings 473 MCDLV4 DOK HB MCDLV4 2E...
Страница 822: ...Protective Elements Name Description Profibus Scada Cmd 16 Scada Command 822 MCDLV4 DOK HB MCDLV4 2E...
Страница 988: ...Protective Elements 988 MCDLV4 DOK HB MCDLV4 2E P P Q P Q P Q Q Q P S S...
Страница 989: ...Protective Elements 989 MCDLV4 DOK HB MCDLV4 2E Pr Q P Q P Qr...
Страница 1023: ...Protective Elements 1023 MCDLV4 DOK HB MCDLV4 2E...
Страница 1070: ...Supervision 1070 MCDLV4 DOK HB MCDLV4 2E...