The VaporGuard® is designed to be placed on a level, stable surface. Versum
Materials, Inc. recommends all electrical connections be made before securing
system to a shelf.
Cables furnished with each system are:
The 3 meter (10 foot) Interconnect Cable connects the Source Cup Assembly to
the Power Supply Module. See Spare Part List in chapter 7.
Optional 3 meter (10 foot) and 5 meter (16 foot) Interconnect, Split cable, sold
separately. See Spare Part List in chapter 7.
Temperature Probe assembly connects to the top of the Source Cup Assembly.
There is only one probe design used for all VaporGuard® models.
The 7.6 meter (25 foot) DDC Cable connects the output signals to the furnace
data lines.
Power Cable for 100-120 VAC provided.
6.3.9
Cable Installation Procedure
Insure SW1 is in the “OFF” position on the Power Supply Module and then connect the
cables in the order given below. Note, installing the J5 connector with the Power
Supply Module on, could result in a hazardous condition.
1.
Attach the Temperature Probe to J7 on Source Cup Assembly.
2.
Install the Interconnect Cable to J9 on Source Cup Assembly and to J4 on Power
Supply Module.
3.
Connect DDC Cable to J5 on Power Supply Module.