SiUS342303E
Test Operation
Part 5 Field Settings and Test Operation
220
3.2 Test Operation Procedure
The procedure below describes the test operation of the complete system. This operation checks
and judges following items:
Check of wrong wiring (communication check with indoor units).
Check of the stop valves opening.
Judgment of piping length.
On top of this system test operation, indoor units operation should also be checked separately.
Make sure to carry out the system test operation after the first installation. Otherwise, the error
code
U3
will be displayed on the remote controller and normal operation or individual indoor unit
test run cannot be carried out.
Abnormalities on indoor units cannot be checked for each unit separately. After the test
operation is finished, check the indoor units one by one by performing a normal operation using
the remote controller. Refer to indoor unit installation manuals for more details concerning the
individual test run.
INFORMATION
It may take 10 minutes to achieve a uniform refrigerant state before the compressor starts.
During the test operation, the refrigerant running sound or the magnetic sound of a solenoid
valve may become loud and the display indication may change. These are not malfunctions.
Procedure
1. Close all front panels in order to not let it be the cause of misjudgment
2. Make sure all field settings you want are set.
3. Turn ON the power to the outdoor unit and the connected indoor units.
NOTICE
Be sure to turn on the power 6 hours before operation in order to have power running to the
crankcase heater and to protect the compressor.
4. Make sure the default (idle) situation is existing. Press the
SET (BS2)
button for 5 seconds or
more. The unit will start test operation.
The test operation is automatically carried out, the outdoor unit display will indicate
t01
and
the indication
Test operation
and
Under centralized control
will display on the remote
controller of indoor units.
Steps during the automatic system test run procedure:
t01
: control before start up (pressure equalization)
t02
: cooling start up control
t03
: cooling stable condition
t04
: communication check
t05
: stop valve check
t06
: pipe length check
t07
: refrigerant amount check
t08
: —
t09
: pump down operation
t10
: unit stop
During the test operation, the progress rate (
1) will be displayed alternately with the display.
During the test operation, it is not possible to stop the unit operation from a remote
controller. To abort the operation, press the
RETURN (BS3)
button. The unit will stop after
around 30 seconds.
1. The progress rate is displayed in
00P
-
99P
, but it may advance rapidly.
Содержание VRV EMERION RXYQ-AATJA
Страница 1: ...Service Manual Heat Pump 60 Hz RXYQ AATJA 208 230 V RXYQ AAYDA 460 V SiUS342303E...
Страница 380: ...Check SiUS342303E 373 Part 6 Service Diagnosis Reference Reference CHECK 7 Refer to page 379 CHECK 8 Refer to page 380...
Страница 405: ...SiUS342303E Wiring Diagrams Part 7 Appendix 398 RXYQ72 96 120 144 168 192 216 240AAYDA C 2D140769B...
Страница 406: ...Wiring Diagrams SiUS342303E 399 Part 7 Appendix 1 2 Indoor Unit FXFQ07 09 12 15 18 24 30 36 48TVJU 3D086460B...
Страница 407: ...SiUS342303E Wiring Diagrams Part 7 Appendix 400 BYCQ125BGW1 Self Cleaning Decoration Panel for FXFQ TVJU 3D076375A...
Страница 410: ...Wiring Diagrams SiUS342303E 403 Part 7 Appendix FXEQ07 09 12 15 18 24PVJU 3D098557A...
Страница 411: ...SiUS342303E Wiring Diagrams Part 7 Appendix 404 FXDQ07 09 12 18 24MVJU C 3D050501C...
Страница 413: ...SiUS342303E Wiring Diagrams Part 7 Appendix 406 FXMQ07 09 12 15 18 24 30 36 48 54PBVJU 3D093209B...
Страница 416: ...Wiring Diagrams SiUS342303E 409 Part 7 Appendix FXHQ12 24 36MVJU 3D048116C...
Страница 417: ...SiUS342303E Wiring Diagrams Part 7 Appendix 410 FXAQ07 09 12 18 24PVJU 3D075354F...
Страница 423: ...SiUS342303E Wiring Diagrams Part 7 Appendix 416 1 3 2 Energy Recovery Ventilator VAM Series VAM300 470 600GVJU 3D073269D...
Страница 424: ...Wiring Diagrams SiUS342303E 417 Part 7 Appendix VAM1200GVJU 3D073270D...