Replacing the BlackDiamond 10808 Switch Fan Tray, Air Filter, and Power Supply Controller
Extreme Networks Consolidated ExtremeXOS Hardware Installation Guide
226
Installing a Power Supply Controller
NOTE
The power supply controllers are hot-swappable. You do not need to turn off power to a BlackDiamond 10808 switch
to install a power supply controller.
To install a power supply controller:
1
Attach the ESD-preventive wrist strap to your wrist and connect the metal end to the ground
receptacle on the top left corner of the BlackDiamond chassis front panel.
2
If a blank faceplate is covering the power supply controller bay, remove it and save it for future use.
3
Verify that the power supply controller is right side up.
4
Slide the power supply controller into the slot, aligning the notch on the top of the slot with the
power supply controller.
5
Tighten the captive thumbscrews to secure the power supply controller into the slot.
Verifying a Successful Installation
After you supply power to the switch, the switch performs a power-on self test (POST).
During the power-on self test:
●
All ports are temporarily disabled.
●
The packet LED is off.
●
The power LED is on.
●
The MGMT LED flashes until the switch successfully passes the POST.
If the switch passes the POST, the MGMT LED blinks at a slow rate (one blink per second). If the switch
fails the POST, the MGMT LED shows a solid yellow light.
Summary of Contents for BlackDiamond 10808
Page 14: ...Table of Contents Extreme Networks Consolidated ExtremeXOS Hardware Installation Guide 14 ...
Page 18: ...Preface Extreme Networks Consolidated ExtremeXOS Hardware Installation Guide 18 ...
Page 19: ...1 Site Preparation ...
Page 20: ......
Page 40: ...Site Preparation Extreme Networks Consolidated ExtremeXOS Hardware Installation Guide 40 ...
Page 41: ...2 BlackDiamond Switches ...
Page 42: ......
Page 93: ...3 Installing BlackDiamond Switches and Modules ...
Page 94: ......
Page 189: ...4 Installing BlackDiamond Switch Accessories ...
Page 190: ......
Page 207: ...5 BlackDiamond Maintenance Procedures ...
Page 208: ......
Page 239: ...6 Summit Family of Switches ...
Page 240: ......
Page 335: ...7 Optics ...
Page 336: ......
Page 363: ...8 Initial Management Access ...
Page 364: ......
Page 369: ...9 Appendixes ...
Page 370: ......